Prefabrication and Full-Scope Carpentry Deliver Speed and Certainty
Elwyn, Pennsylvania
At Elwyn School, Klover is delivering a comprehensive carpentry package that extends from the building envelope through interior finishes. With exterior framing and finishes, vapor barrier, interior framing, drywall, doors, and finishing work all within Klover’s scope, the project demonstrates the advantage of having one experienced team responsible for multiple critical phases of construction.
A major driver of the project’s progress has been prefabrication. Rather than stick framing the building in the field, including its box header details, heavy-gauge framing, and balloon-frame conditions, Klover utilized prefabricated wall panels to accelerate enclosure. According to the project team, conventional field framing could have required approximately two months. Klover’s team set the building’s prefabricated panels in just four days.
From Months of Framing to Four Days
That schedule advantage created momentum that continued throughout the project.
Approximately two and a half months after arriving on site, Klover had completed the exterior framing and vapor barrier, while interior framing was approximately 95% complete and drywall installation was already underway. By moving enclosure forward quickly, the team was able to transition into interior work sooner and keep multiple scopes progressing.
The project also required careful coordination across Klover’s broad scope. Managing prefabricated panels alongside exterior and interior work meant continually planning ahead, coordinating crews, solving field conditions, and adapting as new challenges emerged. For Superintendent Justin Hilligus, that process reflects what makes every Klover project different: understanding what needs to happen next and finding practical solutions that keep people productive and the project moving.
A Complete Carpentry Partner
Klover’s involvement at Elwyn goes far beyond a single trade package. The team’s work spans exterior framing, exterior finishes, vapor barrier, interior framing, drywall, doors, and finishing, creating continuity between the building’s exterior and interior construction.
That breadth allows the field team to look at the project holistically instead of treating each phase independently. Decisions made during framing can account for work that follows, while crews can be planned and coordinated around the overall needs of the project.
Safety Through Every Phase
With multiple scopes progressing simultaneously, safety remains a constant priority. Klover’s safety team works directly with field leadership and crews to identify hazards, verify safe work practices, provide coaching, and address issues as they arise.
The goal is straightforward: everyone goes home the way they came to work.
That commitment is reinforced by a team-oriented approach to problem solving. Construction brings changing conditions, hazards, and unexpected challenges, but the Elwyn team works together to identify solutions and continuously improve how the work gets done.
Building Better, Together
Elwyn School represents the kind of project where Klover’s capabilities come together: prefabrication, field carpentry, interior construction, coordination, safety, and problem solving working as one integrated effort.
From setting an entire prefabricated building in four days to advancing into drywall within the first few months on site, the project demonstrates how planning, prefabrication, and an experienced field team can create meaningful schedule advantages while maintaining the quality and safety expected throughout construction.
For Klover, that progress ultimately comes back to its people. Experienced team members working together, adapting to challenges, and supporting one another are what allow projects like Elwyn to move forward with speed and certainty.
Project Details
- Industry: Academic
- Type: New Construction Prefabrication
- Scope: Doors & Finishes Drywall Exterior Framing Interior Framing Prefabricated Exterior Walls
- Services Provided: Field Carpentry Interior Construction Panel Installation Prefabrication
Watch The Video
Award-Winning Execution
Elwyn School showcases how Klover helps solve complex construction challenges through smarter prefabrication, strategic collaboration, and proven field execution recognized with the 2025 National ABC Eagle Award.
Klover Differentiator
Not Just Installed. Strategically Delivered. Klover combines prefabrication, field expertise, and schedule-focused planning to help teams build with greater certainty.
Why This Project Matters
Elwyn School demonstrates how prefabrication helps projects move faster, reduce labor bottlenecks, and maintain quality on demanding schedules.