Five Decisions to Make Before Prefabricating a Data Center
By Kristian Fields, President and Partner, Klover Contracting
Prefabrication can move portions of data center construction away from a crowded jobsite. Its value depends on what happens before manufacturing begins: selecting suitable assemblies, resolving design requirements, and planning how finished components will reach their installation locations.
The labor context makes that planning increasingly relevant. Associated Builders and Contractors estimated in January that the U.S. construction industry would need to attract 349,000 net new workers in 2026 to meet demand. That estimate covers the broader construction industry, but it gives data center teams a reason to examine how much field labor their delivery plans require.
For wall systems and building enclosures, moving work off-site can allow manufacturing to proceed alongside site activities. However, manufacturing from incomplete information can also produce components that require modification before installation.
Owners, general contractors, and construction managers can use five planning decisions to evaluate that tradeoff before committing a scope to prefabrication.
1. Choose the construction method by assembly
A project can combine factory-built panels, prepared component kits, and conventional field construction. Each method should earn its place through a review of the specific conditions.
Repetitive wall assemblies may suit panelization when their dimensions, shipping requirements, and lifting arrangements are manageable. Kitted prefabrication offers another option: components are prepared to coordinated dimensions, labeled, and grouped for assembly in the field. This can be useful where access or installation conditions make large panels impractical. Areas with unresolved dimensions or frequent changes may need more field flexibility.
Before selecting a method, ask the estimator, fabrication lead, and superintendent to review the same representative assembly. Compare the complete installed scope, including engineering, packaging, freight, lifting equipment, and remaining field work. A lower fabrication price alone does not establish the better delivery method.
2. Establish when each area is ready for manufacturing
Building information modeling, or BIM, helps teams coordinate framing with structural and mechanical, electrical, and plumbing systems. The manufacturing release should identify exactly which information has been reviewed and approved for the scope being produced.
Create a release schedule by area or assembly type. For each package, identify the required drawings, engineering approvals, opening locations, and verified dimensions. Assign responsibility for confirming that those inputs are complete.
A useful distinction is whether an unresolved issue can remain open without affecting the package. An undecided finish may have little effect on one framing assembly. An undecided equipment opening could change its configuration entirely. The responsible design and construction teams should make that determination explicitly.
In a Global Data Center Hub interview, I described starting coordination roughly eight months before product was needed on-site. That is a project-specific example, rather than a standard lead time, but it illustrates how early manufacturing decisions can enter the schedule.
Once a package is released, establish how later revisions will be communicated to the shop and field. Identify affected components and assess the consequences before continuing production.
3. Assign responsibility where systems meet
Panel installation does not complete every part of a wall system. Connections, joints, penetrations, and transitions may involve several contractors, and some work must remain accessible for inspection before it is concealed.
Use a shared interface list to identify who designs, supplies, installs, and inspects each connection between scopes. For an exterior enclosure, that could include the transition from the panel’s weather barrier to adjacent construction. For an interior wall, it could include a service penetration and the firestopping required by the approved assembly.
Walk through one representative condition with the affected trades before production. Confirm the installation order and the access each contractor needs to finish its work. Record the agreed detail and responsible parties in the release package.
This review gives the team a concrete way to uncover gaps that a general statement such as “coordinate with others” can leave unresolved.
4. Plan the route from truck to final position
A delivery plan should account for every movement between the truck and the installed location. Include unloading, temporary storage, building access, lifting arrangements, and any limits on when those activities can occur.
Ask the field team to review the proposed packaging and delivery sequence before manufacturing. A truckload organized for efficient shipping may still require extensive sorting on-site. Labels should connect each panel or kit to its destination and current installation information.
Make a specific plan for exceptions. Where will a damaged panel go? Who checks a kit for missing pieces? What happens if the receiving area is unavailable when the truck arrives? Resolving these questions in advance can prevent a delivery problem from consuming the installation crew’s day.
For work within an operating facility, include the operator’s access restrictions, protection requirements, and approved work windows in this review.
5. Define the milestone the work must support
Measure prefabrication against a useful construction milestone, such as an enclosure ready for follow-on work or an electrical room released for equipment installation. Track the remaining work between panel placement and that milestone.
A room with its framing installed may still need joint treatment, penetration work, inspections, or other activities before the next contractor can begin. Build those dependencies into the schedule and agree on the acceptance criteria with the team receiving the area.
Evaluate total shop and field effort, rework, and material handling alongside installation duration. For repeated areas, compare the first completed package with the plan and adjust subsequent releases or deliveries based on what the crew learned.
Prefabrication can improve a defined construction scope while power availability, equipment delivery, and commissioning continue to govern other parts of the project schedule. Keeping those dependencies visible helps teams state the benefit accurately.
Before authorizing the first manufacturing package, the project team should be able to explain what it is producing, which information supports it, who completes the adjoining work, and how it will reach an accepted installation. Those answers provide a practical basis for deciding where prefabrication belongs in a data center build.
About the author
Kristian Fields is President of Klover Contracting. He holds a bachelor’s degree in civil engineering and spent nearly 16 years at Turner Construction, most recently as Preconstruction Manager for its Philadelphia business unit, before joining Klover. His work focuses on helping owners, developers, and general contractors address complex construction challenges through constructability planning, prefabrication, and integrated design, manufacturing, and installation.